Connecticut Water replaced approximately 1,700 feet, or more than 3/10ths of a mile, of old water main along all or portions of the following streets:

  • Main Street (Talcottville)
  • Elm Hill Road

The new water main has been installed and is in service. We expect permanent paving of construction area to be completed by early July.

 

This project is being done through Connecticut Water’s Water Infrastructure and Conservation Adjustment (WICA). Systematically replacing aging pipes is part of our continuing effort to provide a reliable supply of high quality drinking water and world-class service to customers. This project will help us to conserve water, a precious natural resource, by replacing old pipe that is more likely to leak underground than newer ductile iron pipe.

 

Project is 100% complete
Main Street project is 95% complete

 

 