PROJECT DETAILS
About the project: Connecticut Water will replace about 3,300 feet of existing pipe with 4” & 8” ductile iron pipe. This project will increase available water flow to the area and improve system reliability. Four fire hydrants will be replaced, along with connections to 49 homes.
Location: Church St between Rubber Ave and Division St, Park Place, Barnum Court, and Rubber Avenue between Water St and Church St, Naugatuck
Approximate Start Date: May 15, 2023
Approximate Completion Date: July 2023
Work Hours: 7:00am – 4:30pm, Monday – Friday
Any planned necessary service interruptions will be communicated directly to impacted customers at least 24 hours prior to the interruption.
Please make sure we have your up-to-date contact information by calling 1-800-286-5700 or updating online at ctwater.com/notifications.