South Windsor - Deming Street

Connecticut Water Company (CWC) will be installing water main in your area starting on or about June 21, 2021. The work hours will be 7 a.m. to 4:30 p.m., Monday through Friday.  We expect the project to be complete by the end of September.

Project Letter

Please use caution in the construction work zone.  Our work will involve trenches that may be 6 feet deep.  Our contractor will take all required safety measures to ensure the work area is safe, including: appropriate signs, barricades, and traffic control.  At times traffic lanes may be restricted.  Restoration work, such as repaving of driveway aprons and restoration of grass along the curb line, will take place when the project is fully completed.  Due to seasonal constraints around paving and planting, the restoration work may take place several weeks after we have moved through your area.